Logistic Contractor has signed an agreement with Klinga Logistikpark AB to build a logistics facility in Norrköping. The facility of 31,000 sqm, of which 6,000 sqm in a mezzanine floor, constitutes the first stage in the new logistics park.
The facility will be built in accordance with the customer’s environmental program and designed to provide the opportunity for certification in the future. Among other things, a geothermal heating system will be installed and the roof will be prepared for the installation of solar cells. Construction will start at the beginning of April 2022 and the planned production time is estimated at eleven months.